MIDDLE EAST TESTING SERVICES W.L.L QATAR

GRP Line Testing

Verifying Performance, Safety, and Compliance of GRP Pipelines

Glass Reinforced Plastic (GRP) pipelines have become the preferred choice for water transmission, sewage networks, chemical handling, and industrial applications across the GCC and MENA regions.

Their high strength-to-weight ratio, corrosion resistance, and long service life make them superior alternatives to traditional materials like steel or concrete.

However, verifying the structural and hydraulic integrity of GRP pipelines before commissioning is essential.

At METS Lab, our ISO/IEC 17025-accredited testing services ensure that every GRP system installed meets QCS (Qatar Construction Specifications), AWWA, and ISO standards — safeguarding reliability, safety, and compliance.

1. What is a GRP Line Test?

A GRP Line Test is a pressure integrity assessment conducted on newly installed GRP pipelines to verify that the system:

Is free of leaks and structural defects.

Can safely sustain design operating pressure plus a safety margin (typically 1.5×).

Has all joints, couplings, and fittings correctly installed and fully cured.


It is a mandatory commissioning step before final handover and acceptance by authorities such as Ashghal, Kahramaa, and municipal engineering departments. This ensures long-term performance and regulatory compliance under Gulf environmental and operational conditions.

gloved hand holding test tube by river

2. Testing References and Standards

METS Lab performs GRP testing in accordance with the following key standards and specifications:

  • Qatar Construction Specifications (QCS 2024 – Section 8) – Water Reticulation & Sewerage Works

  • AWWA C950 – Fiberglass Pressure Pipe

  • ISO 10467 – GRP Piping Systems for Pressure and Non-Pressure Applications

  • BS 7159 – Code of Practice for Design and Construction of GRP Piping Systems

  • Manufacturer Installation Manuals – Amiantit, Hobas, Future Pipe Industries, etc.

Each test is conducted following manufacturer-specific tolerances, authority-approved procedures, and traceable QA/QC documentation.


3. Types of Tests Conducted on GRP Pipelines

A complete GRP line testing program typically comprises four major stages, each serving a distinct verification purpose.


1. Visual Inspection (Pre-Test Stage)

Before any pressure testing, a detailed visual and dimensional inspection ensures:

  • Proper alignment and gradient of the pipeline.

  • Correct installation of gaskets, couplings, and anchor blocks.

  • Absence of visible cracks, delamination, or surface defects.

  • Verification that supports and thrust restraints are secure.


This step establishes the baseline condition before hydraulic pressurization.


2. Initial Leak Test (Low-Pressure Test)

The preliminary leak test confirms the basic leak tightness of joints and connections before the main hydrostatic test.

Typical Parameters:

  • Pressure Range: 0.2–0.5 bar (2–5 m water head)

  • Duration: 30 minutes to 1 hour

  • Medium: Water (preferred); air only permitted under strict safety controls for non-pressure lines


This stage helps detect early installation issues before applying full test pressure.


3. Hydrostatic Pressure Test (Main Line Test)

The hydrostatic pressure test is the core integrity test that validates the system’s ability to withstand its design load and environmental stresses.

Procedure Overview:

  • Section Preparation
    • Isolate a test section (typically 300–500 m).

    • Install end caps or blank flanges securely.

    • Fill the pipeline slowly with water, ensuring complete air release via air valves.
  • Stabilization Phase
    • Allow 2–4 hours for temperature equalization and pipe wall absorption.
  • Pressurization Phase
    • Gradually raise the pressure to 1.5 × operating pressure using calibrated pumps.

    • Maintain pressure for a minimum of 1 hour (up to 24 hours if required).
  • Observation & Measurement
    • Record pressure, temperature, and time at fixed intervals.

    • Check for seepage, deformation, or joint movement.

    • Use precision gauges for accurate pressure loss tracking.
  • Acceptance Criteria:
    • No visible leakage at any joint, coupling, or fitting.

    • Pressure drop within allowable limits (manufacturer-defined).

    • No structural deformation, delamination, or blistering observed.

As per AWWA C950, the pressure should remain stable after temperature correction and wall strain stabilization.


4. Deflection and Structural Integrity Tests (If Required)

For buried GRP pipelines, post-installation deflection testing ensures that pipe deformation does not exceed acceptable limits.

Typical Requirements:

Deflection Limit: ≤ 5% of nominal internal diameter.

Methods:

  • Mandrel Testing (physical gauge)

  • Laser Profiling (for large diameters)

These tests confirm that the installed line maintains structural roundness and flow capacity after backfilling and compaction.















4. Test Pressure Calculation

The hydrostatic test pressure is determined using the following equation:

Ptest=1.5×PoperatingP_{test} = 1.5 \times P_{operating}Ptest​=1.5×Poperating​

Example:

If the design operating pressure is 10 bar,

then the test pressure = 15 bar.


⚠️ Important: The applied pressure must not exceed the manufacturer’s maximum allowable test pressure to avoid overstressing the pipe structure.

5. Documentation and QA/QC Records

Each GRP line test performed by METS Laboratories includes comprehensive documentation as part of the QA/QC and handover package:

  • Detailed test report with pipeline section, diameter, and pipe class
  • Calibration certificates for gauges, pumps, and instruments
  • Pressure vs. time graphs with temperature correction data
  • Witness and approval signatures from Contractor, Consultant, and Authority representatives
  • Conformance statement aligned with QCS and AWWA standards

Authority Witnessing

Qatar’s regulatory bodies — Ashghal, Kahramaa, and major industrial facility owners — require official test witnessing and certification prior to issuing completion or commissioning approvals.

gloved hand holding test tube by river

6. Why GRP Line Testing Matters

Verifies Safety: Ensures pipelines can handle operational pressures without leaks or deformation.


Ensures Compliance: Mandatory for QCS, AWWA, ISO, and manufacturer certification.


Prevents Failures: Identifies installation or material issues before costly repairs or environmental damage.


Supports Sustainability: Extends service life through validated performance.


Builds Confidence: Demonstrates quality assurance to contractors, consultants, and end-users.

7. Why Choose METS for GRP Line Testing

  • ISO/IEC 17025-Accredited Testing Laboratory

  • ASHGHAL & Kahramaa-Compliant Procedures

  • Advanced Equipment: Precision pressure gauges, data loggers, laser deflection analyzers

  • Experienced Testing Engineers and QA/QC Inspectors

  • Full Documentation for QCS and AWWA Certification

  • On-Site and Off-Site Testing Support Across GCC

  • Fast Turnaround and Regulatory Liaison Services


With METS Lab, every GRP pipeline is tested not only for pressure — but for trust, reliability, and compliance.

8. Conclusion — Where Engineering Meets Assurance

GRP Line Testing is more than a technical step — it’s the final validation of design, materials, and workmanship.

By adhering to QCS 2024, AWWA C950, and ISO 10467, METS ensures that your pipeline infrastructure performs leak-free, safely, and efficiently under GCC environmental extremes.

In every successful GRP project, testing is where engineering meets assurance — turning design excellence into verified performance.




Stay Informed With METS Laboratories

Connect with us and get to know about our latest updates and service details



Need specialized chemical testing? Share your project details with us, and we'll provide a personalized quote to meet your requirements